Stanisławów – Wola Karczewska
Basic parameters and description of the project:
Project status:
Project route and location:
The investment will be located in the Mazovian Voivodeship, in the following municipalities: Wiązowna, Minsk Mazowiecki, Dębe Wielkie, Stanislawów, Kołbiel.
- high pressure gas pipeline,
- diameter: 700 mm,
- operating pressure: 8.4 MPa,
- length: approx. 38 km.
Project status:
- gas pipeline under engineering design
Project route and location:
The investment will be located in the Mazovian Voivodeship, in the following municipalities: Wiązowna, Minsk Mazowiecki, Dębe Wielkie, Stanislawów, Kołbiel.
The new Stanislawow-Wola Karczewska gas pipeline is a component of the investment program entitled "Construction and modernization of gas infrastructure comprising the new concept of supplying the Warsaw agglomeration". The result of the investment will be a safe and modern natural gas transmission infrastructure, which:
- will enable increased and stable gas transmission to customers from the electric power sector and distribution operators operating in the Warsaw agglomeration,
- will strengthen the energy security of the state and the region,
- will ensure continuity of power supply and reliable gas deliveries to Warsaw and its neighboring municipalities,
- it will also create opportunities to connect new industrial customers, especially from the electricity sector.
The project is implemented on the basis of the provisions of the Act of 24 April 2009 on investments in regasification terminal for liquefied natural gas in Świnoujście (for consolidated text see Journal of Laws of 2021, item 1836).
Under a special act regulating gas infrastructure projects, compensation payments are guaranteed to the owners of the land affected by the project development.
The compensation payment process is carried out in accordance with an administrative procedure, under the supervision of the competent Voivode. First, an independent expert is commissioned to carry out an assessment, which is the basis for determining the amount of compensation. Upon completion of the construction process, the Voivode issues an administrative decision specifying the amount of compensation due.
For more information about the compensation payments and construction process see the section For Landowners.
The compensation payment process is carried out in accordance with an administrative procedure, under the supervision of the competent Voivode. First, an independent expert is commissioned to carry out an assessment, which is the basis for determining the amount of compensation. Upon completion of the construction process, the Voivode issues an administrative decision specifying the amount of compensation due.
For more information about the compensation payments and construction process see the section For Landowners.
Investor:
Gas Transmission Operator GAZ‑SYSTEM S.A.
Oddział w Rembelszczyźnie
ul. Jana Kazimierza 578
05-126 Nieporęt, Rembelszczyzna
phone number. 22 189 08 01
e‑mail: komunikacja.rembelszczyzna@gaz-system.pl
Gas Transmission Operator GAZ‑SYSTEM S.A.
Oddział w Rembelszczyźnie
ul. Jana Kazimierza 578
05-126 Nieporęt, Rembelszczyzna
phone number. 22 189 08 01
e‑mail: komunikacja.rembelszczyzna@gaz-system.pl