Wronów – Rozwadów – Strachocina
![The construction of the gas pipeline is visible from a great height](/dam/jcr:7a3144e0-5427-475b-b6fa-b1eddcddda23/wronow-rozwadow-strachocina-glowna.jpg)
Basic parameters and description of the project:
The gas pipeline is divided by design into two parts:
Project status:
Project route and location:
The preliminary concept of the route runs through the area of 12 counties in the provinces:
- high pressure gas pipeline,
- diameter: 1000 mm,
- working pressure: 8,4 MPa,
- length: approx. 280 km
The gas pipeline is divided by design into two parts:
- Part I: Wronów-Rozwadów gas pipeline with a length of about 120 km.
- Part II: Rozwadów-Strachocina gas pipeline with a length of about 160 km
Project status:
- pipeline under design
Project route and location:
The preliminary concept of the route runs through the area of 12 counties in the provinces:
- lubelskie - counties: puławski, opolski, lubelski, kraśnicki;
- podkarpackie - counties: stalowowolski, niżański, leżajski, łańcucki, przeworski, rzeszowski, brzozowski, sanocki
The gas pipeline is part of an investment program called the Center-East Corridor. Together with the Gustorzyn - Wronów gas pipeline, it will form the main transmission main line in central and southeastern Poland, creating a two-way gas transport route from Lithuania, through Poland to Slovakia, and in the future also reaching Ukraine. This will optimize the operation of the transmission system and ensure security of supply.
The investment is part of the concept of energy transition through the development of the domestic natural gas market and increasing the possibility of connecting industrial consumers, including power and heat generators, to the network.
An important benefit for the local community will be the property tax paid annually by GAZ-SYSTEM in the amount of up to 2% of the value of the transmission infrastructure under construction located in a given municipality. This will be a sum of money regularly flowing into the budget, which can be allocated to the needs of local communities.
The investment is part of the concept of energy transition through the development of the domestic natural gas market and increasing the possibility of connecting industrial consumers, including power and heat generators, to the network.
An important benefit for the local community will be the property tax paid annually by GAZ-SYSTEM in the amount of up to 2% of the value of the transmission infrastructure under construction located in a given municipality. This will be a sum of money regularly flowing into the budget, which can be allocated to the needs of local communities.
The project is implemented on the basis of the provisions of the Act of 24 April 2009 on investments in regasification terminal for liquefied natural gas in Świnoujście (for consolidated text see Journal of Laws of 2024, item 551).
GAZ-SYSTEM is holding information and consultation meetings for property owners who are located in the area of the planned project:
The consultations will be conducted in the form of on-call and individual meetings with residents, with no need for prior registration.
During the talks, interested people will be able to learn about the scope and schedule of the project, the route of the gas pipeline, the procedure for compensation, among other things.
Date | Place of consultation | Commune | Precinct | Detailed information about the consultation |
03.06.2024 12:00 – 17: 00 |
Remiza OSP w Futomie 36-030 Futoma 18 |
BŁAŻOWA | Futoma | Invitation and regulations for consultations |
04.06.22024 12:00 – 17: 00 |
Dom Strażaka 36-203 Izdebki 383A świetlica OSP (parter) |
NOZDRZEC | Wesoła, Hłudno, Izdebki |
Invitation and regulations for consultations |
06.06.22024 12:00 – 17: 00 |
Urząd Gminy Trzydnik Duży 23-230 Trzydnik Duży 59A Sala Konferencyjna pokój 21, II piętro |
TRZYDNIK DUŻY | Trzydnik Mały, Rzeczyca Ziemiańska, Rzeczyca Ziemiańska Kolonia, Zielonka, Łychów Szlachecki, Wola Trzydnicka, Łychów Gościeradowski, Węglin, Węglinek |
Invitation and regulations for consultations |
07.06.22024 12:00 – 17: 00 |
Świetlica w Suchyni ul. Nadrzeczna 40 23-200 Kraśnik |
KRAŚNIK | Niziny, Suchynia, Bojanówka, Podlesie, Góry, Pasieka |
Invitation and regulations for consultations |
10.06.22024 12:00 – 17: 00 |
Urząd Gminy Dzierzkowice Terpentyna 1 23-251 Dzierzkowice Sala Konferencyjna |
DZIERZKOWICE | Terpentyna, Dzierzkowice Zastawie, Dzierzkowice Góry, Dzierzkowice Podwody, Wyżnianka, Wyżnica |
Invitation and regulations for consultations |
25.06.2024 12:00 – 17: 00 |
Dom Strażaka 36-067 Harta 144 |
DYNÓW | Harta, Ulanica, Wyręby, Łubno |
Invitation and regulations for consultations |
26.06.2024 12:00 – 17: 00 |
Urząd Gminy Hyżne 36-024 Hyżne 103 sala konferencyjna, IV piętro |
HYŻNE | Grzegorzówka, Wólka Hyżneńska, Dylągówka, Szklary |
Invitation and regulations for consultations |
During the talks, interested people will be able to learn about the scope and schedule of the project, the route of the gas pipeline, the procedure for compensation, among other things.
Under a special act regulating gas infrastructure projects, compensation payments are guaranteed to the owners of the land affected by the project development.
The compensation payment process is carried out in accordance with an administrative procedure, under the supervision of the competent Voivode. First, an independent expert is commissioned to carry out an assessment, which is the basis for determining the amount of compensation. Upon completion of the construction process, the Voivode issues an administrative decision specifying the amount of compensation due.
For more information about the compensation payments and construction process see the section For Landowners.
The compensation payment process is carried out in accordance with an administrative procedure, under the supervision of the competent Voivode. First, an independent expert is commissioned to carry out an assessment, which is the basis for determining the amount of compensation. Upon completion of the construction process, the Voivode issues an administrative decision specifying the amount of compensation due.
For more information about the compensation payments and construction process see the section For Landowners.
Design engineer:
ANTEA Polska S.A.
ul. Dulęby 5
40-833 Katowice
phone number: 32 358 88 88
e-mail: pl@anteagroup.pl
Investor:
Gas Transmission Operator GAZ-SYSTEM S.A.
Oddział w Tarnowie
Pogórska Wola 450
33-152 Pogórska Wola
phone number. 14 622 53 00
e-mail: komunikacja.tarnow@gaz-system.pl
ANTEA Polska S.A.
ul. Dulęby 5
40-833 Katowice
phone number: 32 358 88 88
e-mail: pl@anteagroup.pl
Investor:
Gas Transmission Operator GAZ-SYSTEM S.A.
Oddział w Tarnowie
Pogórska Wola 450
33-152 Pogórska Wola
phone number. 14 622 53 00
e-mail: komunikacja.tarnow@gaz-system.pl