Mory – Reguły
Basic parameters and description of the project:
Project status:
Project route and location:
The investment will be located in the Mazovian Voivodeship, in the districts of Warsaw West and Pruszków in the following municipalities: Ozarow Mazowiecki, Piastow and Warsaw (Ursus).
- high pressure gas pipeline,
- diameter: 400 mm,
- operating pressure: 8.4 MPa,
- length: approx. 5,2 km.
Project status:
- gas pipeline under engineering design.
Project route and location:
The investment will be located in the Mazovian Voivodeship, in the districts of Warsaw West and Pruszków in the following municipalities: Ozarow Mazowiecki, Piastow and Warsaw (Ursus).
The result of the investment will be a safe and modern natural gas transmission infrastructure that will enable increased and stable transmission of natural gas to customers from the electric power sector and distribution operators operating in the Warsaw agglomeration. Increasing the capacity of the transmission system and the possibility of connecting new customers from the Warsaw agglomeration area.
Improving air quality in the capital and neighboring municipalities by reducing emissions of CO2, sulfur and nitrogen oxides, PM2.5 and PM10 particulate matter.
Local communities will gain an important benefit of the revenue from the property tax to be paid annually by GAZ-SYSTEM S.A. at the rate of 2% of the value of the pipeline section located in the territory of a given commune.
Improving air quality in the capital and neighboring municipalities by reducing emissions of CO2, sulfur and nitrogen oxides, PM2.5 and PM10 particulate matter.
Local communities will gain an important benefit of the revenue from the property tax to be paid annually by GAZ-SYSTEM S.A. at the rate of 2% of the value of the pipeline section located in the territory of a given commune.
The project is implemented on the basis of the provisions of the Act of 24 April 2009 on investments in regasification terminal for liquefied natural gas in Świnoujście (for consolidated text see Journal of Laws of 2021, item 1836).
Environmental decision
On August 12, 2024, the Regional Director of Environmental Protection in Warsaw issued a decision marked: WOOŚ-II.420.33.2024.AGO.14 on environmental conditions for the project entitled “Construction of DN400 8.4 MPa gas pipeline Mory-Reguly ”.
On August 12, 2024, the Regional Director of Environmental Protection in Warsaw issued a decision marked: WOOŚ-II.420.33.2024.AGO.14 on environmental conditions for the project entitled “Construction of DN400 8.4 MPa gas pipeline Mory-Reguly ”.
GAZ-SYSTEM invites to meetings on the proposed Mory-Regula gas pipeline.
Date | Place of consultation | Commune | Precinct | Detailed information about the consultation |
10.07.2024 |
SALA OBRAD RADY MIEJSKIEJ |
PIASTÓW |
PIASTÓW (MIASTO),
|
Invitation and regulations for consultations |
10.07.2024 |
URZĄD MIEJSKI W OŻAROWIE MAZOWIECKIM |
OŻARÓW |
MORY |
|
09.09.2024 17:00 |
DOM KULTURY „MIŚ” OŚRODKA KULTURY „ARSUS” W DZIELNICY URSUS M.ST. WARSZAWY UL. ZAGŁOBY 17 02-495 WARSZAWA |
WARSZAWA (DZIELNICA URSUS) |
Invitation and regulations for consultations |
Under a special act regulating gas infrastructure projects, compensation payments are guaranteed to the owners of the land affected by the project development.
The compensation payment process is carried out in accordance with an administrative procedure, under the supervision of the competent Voivode. First, an independent expert is commissioned to carry out an assessment, which is the basis for determining the amount of compensation. Upon completion of the construction process, the Voivode issues an administrative decision specifying the amount of compensation due.
For more information about the compensation payments and construction process see the section For Landowners.
The compensation payment process is carried out in accordance with an administrative procedure, under the supervision of the competent Voivode. First, an independent expert is commissioned to carry out an assessment, which is the basis for determining the amount of compensation. Upon completion of the construction process, the Voivode issues an administrative decision specifying the amount of compensation due.
For more information about the compensation payments and construction process see the section For Landowners.
Investor:
Gas Transmission Operator GAZ‑SYSTEM S.A.
Oddział w Rembelszczyźnie
ul. Jana Kazimierza 578
05-126 Nieporęt, Rembelszczyzna
phone number. 22 189 08 01
e‑mail: komunikacja.rembelszczyzna@gaz-system.pl
Gas Transmission Operator GAZ‑SYSTEM S.A.
Oddział w Rembelszczyźnie
ul. Jana Kazimierza 578
05-126 Nieporęt, Rembelszczyzna
phone number. 22 189 08 01
e‑mail: komunikacja.rembelszczyzna@gaz-system.pl