Connection of the Kozienice Power Plant in Świerże Górne

gas pipeline infrastructure
Basic parameters and description of the project:
  • high pressure gas pipeline,
  • diameter: 700 mm,
  • operating pressure: 8.4 MPa,
  • length of approx. 20 km.

Project status:
  • gas pipeline under design.

Project route and location:
The gas pipeline will be located in the Mazovia Voivodeship, Kozienice County. Its route will cross the municipalities of: Głowaczów i Kozienice.A map showing the connection process to Kozienice Power Plant

Benefits

The connection pipeline to the Kozienice Power Plant in Swierże Górne will provide real opportunities to introduce - as part of the energy transition - changes in generation technology based on the use of low-carbon fuel sources. 

The municipalities will gain an important benefit of the revenue from the property tax to be paid annually by GAZ-SYSTEM at the rate of 2% of the value of the pipeline section located in their territory. The owners of the properties to be crossed by the gas pipeline will receive compensation in this respect and will still be able to use their land.

Public consultations

GAZ-SYSTEM invites public consultations on the connection pipeline to the Kozienice Power Plant project.
 
Date Place of consultation  Commune Precinct  Detailed information about the consultation
13.09.2023
11:00 – 17:00
Urząd Gminy Głowaczów
Adres siedziby:
ul. Rynek 25
26-903 Głowaczów
Głowaczów Bobrowniki, Miejska Dąbrowa, Podmieście, Głowaczów, Lipa, Leżenice, Moniochy, Emilów, Michałów, Grabnowola, Chodków Invitation and regulations for consultations (PL)
14.09.2023
10:00 – 16:00
Ochotnicza Straż Pożarna w Świerżach Górnych
Adres siedziby: 
59A, Świerże – Górne, 
26-900 Kozienice
Kozienice Wola Chodkowska, Selwanówka, Łaszówka I, Świerże Górne
The consultations will take the form of one-on-one meetings with residents, with no pre-registration required.

Compensation payments

Under a special act regulating gas infrastructure projects, compensation payments are guaranteed to the owners of the land affected by the project development.

The compensation payment process is carried out in accordance with an administrative procedure, under the supervision of the competent Voivode. First, an independent expert is commissioned to carry out an assessment, which is the basis for determining the amount of compensation. Upon completion of the construction process, the Voivode issues an administrative decision specifying the amount of compensation due.

For more information about the compensation payments and construction process see the section For Landowners.

Contacts to Contractors and Investor

Design engineer:
OTS-IP Sp. z o.o. 
ul. Kapelanka 26
30-347 Kraków
phone number. +48 722 175 161
e-mail: ots-ip@ots-ip.pl 

Investor:
Operator Gazociągów Przesyłowych GAZ-SYSTEM S.A.
Oddział w Rembelszczyźnie
ul. Jana Kazimierza 578
05-126 Nieporęt, Rembelszczyzna
phone number. 22 767 08 01
e-mail: komunikacja.rembelszczyzna@gaz-system.pl