Gas pipeline construction
Basic parameters and description of the project:
  • high pressure gas pipeline,
  • diameter: 1000 mm,
  • minimum foundation depth: 1.2 m below ground level,
  • operating pressure: 8.4 MPa,
  • length: approx. 34 km.
The construction of the Kolnik - Gdańsk gas pipeline is directly connected with the implementation of the FSRU (Floating Storage Regasification Unit) Project which involves the development of a floating LNG terminal in the Gdańsk area to receive the liquefied natural gas delivered by sea.

Project status:
  • On November 7, 2024, a general contract for the construction of the Kolnik - Gdansk gas pipeline was signed. PORR S.A., based in Warsaw, became the contractor for construction works. 
  • Commencement of construction works Q1 2025.
  • Planned completion date of construction works 2026. 

Project route and location:
The gas pipeline Kolnik - Gdańsk together with the accompanying infrastructure will be implemented in the Pomeranian Voivodeship in the Municipalities of Gdańsk, Pruszcz Gdański, Cedry Wielkie, Suchy Dąb, Pszczółki and in the geodesic precincts:  Pszczółki Commune: Kolnik, Pszczółki. Suchy Dąb municipality: Koźliny, Krzywe Koło, Suchy Dąb, Osice. Cedry Wielkie Commune: Trutnowy, Koszwały, Miłocin.  Gmina Pruszcz Gdański: Wiślinka, Bogatka, Przejazdowo. City of Gdansk: 300S, 271S, 273S, 270S.
Map of gas pipeline Kolnik-Gdańsk

Infromation meetings

GAZ-SYSTEM invites you to informational meetings for the Kolnik-Gdansk:
   
Date Place of meeting Commune Precinct Information posters
24.10.2024 r.
17:00-19:00
Szkoła Podstawowa nr 62, ul. Kępna 38; 80-638 Gdańsk Gdańsk Gdańsk   Information poster
10.12.2024 r.
16:00
Gminna Biblioteka Publiczna w Pszczółkach 
ul. Kościelna 8A, 83-032 Pszczółki 
Pszczółki   Information poster
10.12.2024 r.
18:30
Żuławski Ośrodek Kultury i Sportu w Cedrach Wielkich  
ul. Osadników Wojskowych 8,
83-020 Cedry Wielkie
Cedry Wielkie   Information poster
12.02.2025 r.
16:00
Szkoła Podstawowa nr 62,
ul. Kępna 38;
80-638 Gdańsk 
Gdańsk   Information poster

Benefits

The new pipeline will enable the off-take of additional gas volumes from the FSRU terminal located in the Gdańsk area. The investment will improve the capacity of the Polish transmission system and thus contribute to strengthening Poland's energy security.
 
The construction of new transmission infrastructure will also stimulate the development of the gas market and its competitiveness.

Local communities will gain an important benefit of the revenue from the property tax to be paid annually by GAZ-SYSTEM at the rate of 2% of the value of the transmission infrastructure section to be located in the territory of each municipality. This amount will be a regular contribution to the local budget which may be spent on community needs.

Project of Common Interest (PCI)

The European Commission has granted the PCI (Project of Common Interest) status to the project. More information on the significance of the PCI status for the development of gas transmission infrastructure can be found in the  dedicated section on PCI projects.

While implementing its investment projects GAZ-SYSTEM S.A. respects the rights of all interested stakeholders. We encourage you to send comments and questions concerning the project which has been granted the PCI using the Form for questions and comments concerning the implementation of projects with PCI status by GAZ- SYSTEM.

Public consultations

A series of public consultation meetings were held in April and May 2021 for each commune along the route of the proposed gas pipeline. 

Invitations to the meetings were sent both electronically and in printed form to the communes concerned, and through them to: village heads, local communities and owners of properties through which the project is to run.

The consultations were held in the form of one-on-one meetings with the residents (among other reasons due to epidemic restrictions), during which each participant could get to know the route of the planned gas pipeline and its course through their property. Representatives of the investor and the engineering company were also present and answered questions concerning, among other things, the safety of the infrastructure, compensation payments, legal basis for the project and timing of further works.

Within 7 days of the end of the consultations, each resident could express their reservations as to the route. 
 

Administrative decisions

Environmental decision:
  • On 5 July 2021, the Regional Director for Environmental Protection in Gdańsk issued the first environmental decision (no. RDOŚ-Gd-WOO.420.67.2020.KSZ.32) for the approx. 1.2 km-long section of the Kolnik-Gdańsk gas pipeline.
  • On 21 July 2021, the Regional Director for Environmental Protection in Gdańsk issued the second environmental decision (No. RDOŚ-Gd-WOO.420.59.2020.AJM/IK.39) for the remaining part of the Kolnik-Gdańsk gas pipeline.
Decision on location:
  • On 3 December 2021 Pomorskie Voivode issued a first decision on the location (no WI-III.747.1.19.2021.AM) for the onshore section of the Kolnik - Gdańsk gas pipeline connecting the floating terminal with the national transmission system.
  • On 12 December 2021 Pomorskie Voivode issued a second decision on the location (no WI-III.747.1.23.2021.AM) for the remainder of the Kolnik - Gdańsk gas pipeline.
Building permit decision:
On 21.06.2022, a set of decisions approving construction designs and granting construction permits were obtained for the following investment tasks, among others:
  • Kolnik-Gdansk gas pipeline with a diameter of DN1000 and pressure of 8.4 MPa,
  • high-pressure connection gas pipeline of the FSRU-Dry Weld Metering Station together with the metering station and fiber optic cable.

Compensation payments

Under a special act regulating gas infrastructure projects, compensation payments are guaranteed to the owners of properties affected by the project development.

The compensation payment process is carried out in accordance with an administrative procedure, under the supervision of the competent Voivode. First, an independent expert is commissioned to carry out an assessment, which is the basis for determining the amount of compensation. Upon completion of the construction process, the Voivode issues an administrative decision specifying the amount of compensation due.

For more information about the compensation payments and construction process see the section For Landowners.

Contacts to Contractors and Investor

Hotline:
887 060 938

Design engineer: 

Ramboll Polska Sp. z o.o.
ul. Bitwy Warszawskiej 1920 r. 7
02-366 Warszawa
phone number. 22 372 0050; 22 372 0054
e-mail: rpl-biuro@ramboll.com

Construction Contractor:
PORR S.A.
123 Holubcowa St.; 02-854 Warsaw 
Construction Office: 
Gdańska 109,
83-031 Różyny 
tel.  519 795 670

Investor's Supervision Contractor:
ECM Group Polska S.A. 
Rondo ONZ 1,
00-124 Warsaw
Office:
Address: 46 30 Stycznia Street (floor 1),
83-110 Tczew 
Tel. 886 511 497

Investor:
Gas Transmission Operator GAZ-SYSTEM S.A.
Oddział w Gdańsku
ul. Wałowa 47
80-858 Gdańsk
phone number. +48 58 744 05 00
e-mail: sekretariat.gdansk@gaz-system.pl