Leśniewice – Rawa Mazowiecka (stage II Gustorzyn - Wronów)

The construction of the gas pipeline is visible from a great height
Basic parameters and description of the project:
  • high pressure gas pipeline,
  • diameter: 1000 mm,
  • working pressure: 8,4 MPa,
  • length: approx. 100 km

Project status:
  • The construction of the Gustorzyn - Wronow gas pipeline was completed in 2023. 

Project route and location:
The gas pipeline is located in the Mazovian and Łódź Voivodeships. The route pass through the territory of 15 municipalities: Gostynin; Szczawin Kościelny; Pacyna; Oporów; Bedlno; Żychlin; Zduny; Łowicz; Łyszkowice; Maków; Godzianów; Głuchów; Skierniewice; Nowy Kawęczyn; Rawa Mazowiecka.
Map Leśniewice-Rawa Mazowiecka

Benefits

The aim of the project was to build a high pressure gas pipeline from Gustorzyn to Leśniewice, which will enable the transmission of increased volumes of gas to Warsaw and Łódź agglomerations, Radom and its surroundings, and to the south-eastern regions of the country. The planned investment has also have an impact on the development of local infrastructure.

An important benefit for the local community is the property tax paid annually by GAZ-SYSTEM in the amount of up to 2% of the value of the transmission infrastructure under construction located in the territory of a given municipality. This amount is regular contribution to the local budget which may be spent on community needs.

Co-financing by the European Union

The construction of the gas pipeline received funding under Measure 11.2 Support for smart gas infrastructure for energy transition under Priority Axis XI of REACT-EU OPI&E 2014-2020.
 

Project of Common Interest (PCI)

The European Commission has granted the PCI (Project of Common Interest) status to the project. More information on the significance of the PCI status for the development of gas transmission infrastructure can be found in the  dedicated section on PCI projects.

While implementing its investment projects GAZ-SYSTEM S.A. respects the rights of all interested stakeholders. We encourage you to send comments and questions concerning the project which has been granted the PCI using the Form for questions and comments concerning the implementation of projects with PCI status by GAZ- SYSTEM.

Public consultations

Public consultations were organised in connection with the implementation of the project. The consultation events held to date and their schedule are presented below.

Administrative decisions

Environmental decision:
  • Decision No. 4/2020 issued by the Regional Director for Environmental Protection in Łódź on 22 January 2020.
Decisions establishing the location:
  • Decision establishing the location of the investment project associated the LNG terminal project No. 80/SPEC/2020 issued by the Mazowiecki Voivode on 21 July 2020.
  • Decision establishing the location of the investment project No. 2/2020 issued by the Łódzki Voivode on 21 July 2020.
  • Decision establishing the location of the investment project No. 4/2020 issued by the Łódzki Voivode on 21 September 2020.
Building permit:
  • Building permit No. 523/SAAB/2021 for an investment project associated with the LNG terminal project, dated 4 August 2021 issued by the Mazowiecki Voivode
  • Building permit No. 77/21 for an investment project associated with the LNG terminal project, dated 4 June 2021 issued by the Łódzki Voivode
  • Building permit No. 98/21 for an investment project associated with the LNG terminal project, dated 1 July 2021 issued by the Łódzki Voivode

Compensation payments

Under a special act regulating gas infrastructure projects, compensation payments are guaranteed to the owners of the land affected by the project development.

The compensation payment process is carried out in accordance with an administrative procedure, under the supervision of the competent Voivode. First, an independent expert is commissioned to carry out an assessment, which is the basis for determining the amount of compensation. Upon completion of the construction process, the Voivode issues an administrative decision specifying the amount of compensation due.

For more information about the compensation payments and construction process see the section For Landowners.

Contacts to Contractors and Investor

Design engineer was:
consortium firm ILF Consulting Engineers Polska Sp. z o.o. oraz PGNiG GAZOPROJEKT S.A

Building Contractor:
Consortium: ROMGOS Sp. z o.o. ENGINEERING Sp. k. (Lider Konsorcjum),  oraz ROMGOS Gwiazdowscy Sp. z o.o. oraz Przedsiębiorstwo Budowlano-Melioracyjne TOLOS Piotr Walczak i wspólnicy Sp.k.

Romgos Sp. z o.o.
Construction Office w Kutnie
ul. Poprzeczna 3 99-300 Kutno
phone numeber. +48 782 888 970
e-mail: m.kupiec@romgos.pl

Construction manager:
Dominik Czarnecki
phone number: + 48 574 330 730
e-mail: d.czarnecki@romgos.pl

Inwestor:
Gas Transmission Operator GAZ-SYSTEM S.A.
Oddział w Rembelszczyźnie
ul. Jana Kazimierza 578
05-126 Nieporęt, Rembelszczyzna
phone numeber. +48 22 220 11 37
e-mail: komunikacja.rembelszczyzna@gaz-system.pl