Gas pipeline under construction
Project description:
  • high pressure pipeline
  • diameter - DN 1000
  • MOP - 8.4 MPa
  • length- approx. 191 km
​​​
Investment status:
  • The investment has been completed.

Location:
The pipeline construction process was divided to two stages:
  • Stage 1: Gas pipeline section between Goleniów and Ciecierzyce, with a length of approx. 122 km,
  • Stage 2: Gas pipeline section between Ciecierzyce and Lwówek, with a length of approx. 69 km.

The gas pipeline was developed in three voivodeships: Zachodniopomorskie, Lubuskie and Wielkopolskie, in the communes of: Goleniów, Maszewo, Stargard, Dolice, Przelewice, Pełczyce, Strzelce Krajeńskie, Zwierzyn, Santok, Deszczno, Skwierzyna, Przytoczna, Pszczew, Międzychód, Lwówek.
Map of Goleniów-Lwówek and compressor stations

Benefits

The new pipeline provide the capacity to off take incremental gas volumes from the Baltic Pipe offshore pipeline and the LNG Terminal in Świnoujście. The investment optimise the capacity of the Polish transmission system and constitute an important link of the North-South Gas Corridor in Europe.

Furthermore, the completion of the Baltic Pipe Project, of which this project makes part, strengthen Poland’s energy security. The construction of new transmission infrastructure also stimulate the development of the gas market and its competitiveness.

The municipalities where the gas pipeline was built will benefit significantly from the taxes to be paid annually by GAZ-SYSTEM.

EU co-financing

The Baltic Pipe Project, of which the construction of the Goleniów-Lwówek gas pipeline makes part, is co-financed by the European Union under the Connecting Europe Facility (CEF).

Project of Common Interest (PCI)

The European Commission has granted the PCI (Project of Common Interest) status to the project. More information on the significance of the PCI status for the development of gas transmission infrastructure can be found in the  dedicated section on PCI projects.

While implementing its investment projects GAZ-SYSTEM S.A. respects the rights of all interested parties. You are encouraged to send comments and questions concerning any project which was granted the PCI status using the Form for questions and comments concerning the implementation of projects with PCI status by GAZ- SYSTEM.

Administrative decisions

Environmental consultations
On October 9, 2018, the Regional Director for Environmental Protection in Gorzów Wielkopolski announced the initiation of proceedings to issue a decision on environmental conditions for the construction of Goleniów-Lwówek DN 1000 gas pipeline.

Documentation was prepared for the project, including an application for an environmental decision and an EIA report.

On December 12, 2018, the Regional Director for Environmental Protection in Gorzów Wielkopolski notified all interested parties of the possibility to review the documentation of the case, and to submit comments and motions within 30 days.

The details of this announcement can be found here.

Environmental decision
On February 4, 2019, the Regional Director of Environmental Protection in Gorzów Wielkopolski issued a decision on environmental conditions ref. no. WZŚ.420.140.2018.SL for the project named: “Construction of the Goleniów-Lwówek DN 1000 gas pipeline”.

This is the first environmental decision for the Baltic Pipe Project.

Location decision
Location decisions for the Construction of the Goleniów - Lwówek gas pipeline, DN1000 were issued by the Governors of Wielkopolskie and Zachodniopomorskie Voivodeships, respectively, on 15 May 2019 and on 17 May 2019.

On June 14, 2019, the Governor of Lubuskie Voivodeship issued two location decisions for the construction of Goleniów-Lwówek  DN1000 gas pipeline.

Building permits
On January 7, 2020, the Governor of Wielkopolskie Voivodeship issued the first building permit for the Goleniów - Lwówek DN1000 gas pipeline, Stage 2 Ciecierzyce - Goleniów, making part of the onshore section of the Baltic Pipe Project.

On January 21, 2020, the Governor of Zachodniopomorskie Voivodeship issued a building permit for Stage 1, i.e. the Goleniów - Ciecierzyce gas pipeline making part of the onshore section of the Baltic Pipe Project.

On February 28, 2020, the Governor of Lubuskie Voivodeship issued a building permit for Stage 1, i.e. the Goleniów - Ciecierzyce gas pipeline, and Stage 2, i.e. the Ciecierzyce - Lwówek gas pipeline.

Public consultations

In 2018, GAZ-SYSTEM held a series of consultation meetings in the municipalities where the Goleniów-Lwówek gas pipeline was planned. The meetings were open to all interested parties. The purpose of the consultations was to provide information on the Baltic Pipe Project, including the planned gas pipeline Goleniów – Lwówek, and to prepare the local community for official environmental consultations. During the meetings, stakeholders were able to provide feedback and requests concerning the project to the Investor at the design stage, still before the application for the environmental decision was submitted.

Compensation payments

Under a special act regulating gas infrastructure projects, compensation payments are guaranteed to the owners of properties affected by the project development.

The compensation payment process is carried out in accordance with an administrative procedure, under the supervision of the competent Voivode. First, an independent expert is commissioned to carry out an assessment, which is the basis for determining the amount of compensation. Upon completion of the construction process, the Voivode issues an administrative decision specifying the amount of compensation due.

For more information about the compensation payments and construction process see the section For Landowners.

Contacts to Contractors and Investor

Design engineer:
MGGP S.A.
ul. Kaczkowskiego 6
33-100 Tarnów
phone number.  +48 (14) 626 38 90
e-mail: mggp@mggp.com.pl

Investor’s Supervision Contractor:
 
  • Stage I - Goleniów – Ciecierzyce - ECM Group Polska S.A;
ECM GROUP Polska S.A.
CENTRALA
00-124, Warszawa
ul. Rondo ONZ 1
phone number. +48 22 333 73 57
e-mail: office@ecmg.pl

Subcontractor:
Przedsiębiorstwo Usług Inwestycyjnych EKO-INWEST S.A.
P.U.I. EKO-INWEST S.A.
ul. Jerzego Zimowskiego 20
71-281 Szczecin
e-mail: biuro@eko-inwest.com.pl
 
  • Stage II - ECM Group Polska S.A.
ECM GROUP Polska S.A.
CENTRALA
00-124, Warszawa
ul. Rondo ONZ 1
phone number. +48 22 333 73 57
e-mail: office@ecmg.pl

Subcontractor:
KOMPLET INWEST z o. o
ul. Małorolnych 24
66-400 Gorzów Wielkopolski

Building Contractor:
 
  • Stage I - Goleniów – Ciecierzyce - spółka Budimex S.A.
Budimex S.A.
ul. Siedmiogrodzka 9
01-204 Warszawa

Construction Office:
ul. Metalowa 17
73-110 Stargard 
 
  • Stage II - Ciecierzyce – Lwówek - spółka JT S.A
JT S.A.
ul. Płochocińska 111
03-044 Warszawa
phone number. +48 22 632 56 05

Construction Office:
J.T. S.A.
ul. Walczaka 25 A  
66-400 Gorzów Wielkopolski

Investor
Gas Transmission Operator GAZ-SYSTEM S.A.
Oddział w Poznaniu
ul. Grobla 15
61-859 Poznań
phone number. +48 61 854 45 03
e-mail: komunikacja.poznan@gaz-system.pl