Construction of the connection
Standard connection process (approximately 36 months).
Handing over the mutually signed connection agreement:
Handing over the mutually signed connection agreement:
- Drafting of tender documents (2 months).
- Announcement of tender for project engineering documentation (2 months).
- Signing of the contract with the Contractor for the engineering documentation (obtaining necessary administrative decisions) (10 months).
- Announcement of tender for the Construction Works Contractor (2 months).
- Signing of the contract with the Construction Works Contractor and handing over the construction site to the Contractor (18 months).
- Technical acceptance, obtaining a permit to operate and final commissioning (2 months).
- Project settlement.