Gas compressor station infrastructure
Standard connection process (approximately 36 months).
Handing over the mutually signed connection agreement:
  1. Drafting of tender documents (2 months).
  2. Announcement of tender for project engineering documentation (2 months).
  3. Signing of the contract with the Contractor for the engineering documentation (obtaining necessary administrative decisions) (10 months).
  4. Announcement of tender for the Construction Works Contractor  (2 months).
  5. Signing of the contract with the Construction Works Contractor and handing over the construction site to the Contractor (18 months).
  6. Technical acceptance, obtaining a permit to operate and final commissioning (2 months).
  7. Project settlement.