Occupancy permit issued for Hermanowice-Strachocina gas pipeline
- construction of a 72 km long high pressure gas pipeline along with a fibre-optic line;
- extension of the distribution and measurement station in Hermanowice;
- construction of five shut off and relief valve systems;
- construction of a cathode protection station within Kuźmin shut off and relief valve system.
- San river crossing in Mrzygłód, using the HDD technology (HDD), featuring the length of almost 980 meters;
- 8 crossings using the micro-tunneling technology;
- 27 crossings under roads, railway lines and watercourses using the HDD technology.
- Design documentation contractor - GAS STORAGE POLAND sp. z o.o.
- General Contractor for Construction Works - PGNiG Technologie S.A.
- Investor’s Supervision Contractor - MGGP S.A.
- Author's Supervision Contractor - ILF Consulting Engineers Polska sp. z o.o.